Queensland-wide commercial switchboard project delivery
CASE STUDY

EV Charging and Your Commercial Switchboard: A Proven 2026 Guide

A commercial switchboard sized for EV charging load, EV Charging Switchboard Upgrades across Brisbane and South East Queensland

The Real Problem

Site
Sector
Scope
Tenants affected
Duration
Trading disruption
Supply authority
Standards

QUICK ANSWER

EV charging adds significant continuous load to a site, and many commercial switchboards do not have the spare capacity to support it. Before installing chargers, the switchboard and supply need to be assessed. Often the board needs more capacity, load management, or an upgrade, and larger installations may trigger a supply increase and CT metering through Energex.

Adding EV charging to a commercial site sounds simple, but the chargers are only half the job. The real question is whether your switchboard and supply can handle the extra load. EV chargers draw heavy, sustained current, and bolting them onto a board that is already near capacity is a fast way to cause nuisance tripping, overheating or a failure. This guide explains how EV charging affects your commercial switchboard and what to check before you install.

Commercial switchboard capacity for ev charging load
EV charging adds significant load, so the commercial switchboard often needs spare capacity or an upgrade.

Why EV charging is a big load

A single fast commercial EV charger can draw as much power as a large part of a small building. Unlike intermittent loads, charging runs at a high, steady current for long periods. Multiply that across several chargers in a car park and the demand on the commercial switchboard is substantial. The board, the main switch, the cabling and the supply all have to be sized for it, which is exactly what older boards were never designed for.

Key point: the chargers are the easy part. Whether your commercial switchboard and supply can carry the load is what decides the real scope and cost of an EV charging project.

What to check before installing EV chargers

  • Spare capacity on the existing switchboard and main supply
  • The rating of the main switch, busbars and incoming cabling
  • Whether load management can spread demand across chargers
  • If a supply increase and CT metering are needed
  • Compliance of the board for the new circuits and protection

Options for supporting EV charging

Situation Typical solution
Board has spare capacity Add protected circuits for the chargers
Limited capacity Load management to share available supply
Insufficient capacity Switchboard upgrade and possible supply increase
Large installation Supply upgrade with CT metering via Energex

When EV charging needs a switchboard upgrade

If the board is already near capacity, adding EV charging usually means a switchboard upgrade to increase capacity and add compliant, protected circuits. For larger installations the supply itself may need increasing, which brings in CT metering and Energex coordination. Planning this up front avoids installing chargers that trip the board or cannot all run at once.

Load management vs upgrading

Worth remembering: load management can let you add EV charging without a full upgrade by sharing the available supply between chargers. It is a good interim step, but if demand keeps growing, a switchboard upgrade gives you headroom rather than constantly rationing power.

Why use a switchboard specialist

EV charging is a switchboard and supply question as much as a charger question. Because switchboards are all we do, we assess the board and supply, design the capacity and protection, coordinate any supply increase with Energex, and make sure the commercial switchboard safely supports the chargers now and as you add more.

EV charging and switchboards: frequently asked questions

Does EV charging need a switchboard upgrade?
Often yes. EV chargers add heavy continuous load, so if the board is near capacity it usually needs an upgrade to add capacity and compliant circuits.

How much load does a commercial EV charger add?
A fast commercial charger draws a high, steady current for long periods, comparable to a large portion of a small building, which is why the board and supply must be sized for it.

What is load management for EV charging?
Load management shares the available supply between chargers so you can add EV charging without exceeding the board capacity, often avoiding a full upgrade.

Will EV charging need a supply increase?
For larger installations, yes. A supply increase brings in CT metering and Energex coordination as part of the project.

What should I check before installing EV chargers?
The spare capacity of the switchboard and supply, the rating of the main switch and cabling, and whether load management or an upgrade is needed.

Who should assess my switchboard for EV charging?
A specialist switchboard contractor who can assess the board and supply and design the capacity and protection to AS/NZS 61439.

Related guides

Standards and references

About the author

Anthony Nuich is the owner of Commercial Switchboards, the specialist switchboard division of SEQ Sparky Pty Ltd, holding QLD Electrical Contractor licence #90899. With 10+ years assessing and upgrading commercial switchboards for new loads across Brisbane and Queensland, Anthony reviews every project personally.

If you are planning EV charging and need to know whether your commercial switchboard can handle it, request an initial project review.

The Real Problem

Related

Credentials

GOT A SIMILAR PROJECT?

Shopping centre meterboard upgrade in your portfolio?

Send through your centre details, current meterboard photos, tenant count and any defect notices — we’ll review and respond within one business day.